Monthly Archives: July 2016

August 1 -5 CF Road Construction Update

The schedule for work Aug 1-5 on Cedar Falls Road includes both day and night shifts. Monday  -  day work, shoulder prep Tuesday – day work,  shoulder prep and clean up                    night work, paving the road Wednesday – day work, … Continue reading

Posted in Announcements | Comments Off

July 25-29 CF Road Construction Update

The schedule for work July 25-29 on Cedar Falls Road includes both day and night shifts: Monday – day work, tie in new mainline Tuesday – day work, install PRV Wednesday – night work, trench patch Thursday – day work, trench … Continue reading

Posted in Uncategorized | Comments Off

July 19 CFR Construction Update

Denny Scott, our Water System Superintendent, has an update for today’s construction schedule.  The crews will be working on the inter-tie near Riverbend from approximately 2:30-4:30 PM Tuesday, July 19.   Please plan for delays as the road is cut … Continue reading

Posted in Announcements | Comments Off

July 18-21 Cedar Falls Road Construction Schedule

The construction crew will begin working during the day starting Monday the 18th through Thursday the 21st of July.  Possible lanes closures will be between 9am and 3pm only.  There may be workers before 9am or after 3pm but they … Continue reading

Posted in Announcements | Comments Off

Cedar Falls Construction Update

The week of July 10-15, Sallal will be working on the pipe installation on Cedar Falls Road from Monday – Thursday evenings, 7PM-6AM.  Please check the website for updates as the project progresses and thank you for your patience during … Continue reading

Posted in Announcements | Comments Off